STATUS REPORT OF WORKS (KARIMGANJ DISTRICT) AS ON 31ST DECEMBER 2022
Sl. No. |
Name of Ongoing Scheme |
Sanctioned Estimated Amount (in Lakh) |
Name of Contractor |
Date of commencement |
Target date of completion |
Achivement |
Remarks |
|||
Physical |
Total length Completed (in Km) |
Financial (in Lakh) |
||||||||
Upto date progress (%) |
Expected progress of Next Month |
|||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
|
||||||||||
2 |
Balance work of “Improvement of existing single / Intermediate lane of NH-44 to 2 lane with paved shoulder from Km 230/200 to Km 247/000, Km 261/504 (Ex. Ch.- 260/109) to Km 263/191 (Ex. Ch.261/761) and Km 272/241 (Ex. Ch. 271/000) to Km 284/033 (Ex. Ch. 284/053) (Total Length=30.28Km) under SARDP-NE (Phase-A) in the State of Assam (Job No.-SARDP-NE/NH-44/AS/PWD/2010-11/182)” |
16694.00 (L) |
Dipayan Paul & Chanchal Paul |
17/12/2020 |
715 days (From date of appointment i.e on 02/12/2022
|
88.00% |
100.00% |
26.706Km |
Rs. 11188.00 (L) |
Work is in progress. EOT applied for 60(sixty) days i.e upto 31/01/2023. |