PWD Buildings
INTRODUCTION
The Assam Public Works Department was established in the year 1880. The department has undergone considerable expansion since after attainment of independence and for smooth functioning of the organization, to share the increasing work load and for providing more stress to development works, the Assam P.W.D. has been divided into two wings viz. Roads and Building wings in August 1977 and since then both the wings are functioning with their prescribed identity. The principal function of the Public Works Department is to develop the infra-structure for transport & communications of the State. Assam P.W.D. discharges its function in construction and repair of roads, bridges, culverts in the state including construction and repair of public buildings of the state and till date it has reached a considerable height of fame and competence.
Public Works Department(Building Wing) deals with the construction, maintenance and repair of Government Buildings and structures in the state of Assam and also outside Assam for construction of Assam Bhawan etc.
Key Functions:-
(i) Construction, repair and maintenance of various Government and residential building of the State.
(ii) Adoption and implementation of the latest standards, State of the Art practices, use of innovative and appropriate technology and building materials to enhance quality, productivity and affordability.
PROGRESS REPORT FOR THE MONTH OF DECEMBER '2022 OF KARIMGANJ DISTRICT UNDER KARIMGANJ DISTRICT TERRITORIAL BUILDING DIVISION, KARIMGANJ | ||||||||||||||
Sl. No. | Name of Project / Works | Head of Account | A.A No. and Date | A/A Amount | Tender Value (Rs) | Formal work order and Date | Name of contractor | Date of completion as per FWO | Up to date Physical Progress of Civil & Electrical works (in%) | Financial Progress of Civil & Electrical works(in Lakhs/%) | Action taken against defaulting contractors with details. | Remarks | ||
Previous month | Dec '22 | Previous month | Dec.'22 | |||||||||||
CULTURAL DEPTT. (Karimganj Dist.) | ||||||||||||||
1 | Construction of 1000 capacity Auditorium at R.K. Nagar, Karimganj, Assam | 4059-01-101-0121-227-13-99-SOPD-G-V-GA | AA/PWB_2020-21(I)_1134 dt.17.09.2020 | Rs.1390.04800 (L) | 92086724.00 | ADP/49/ 2019/24 dt.19.10.2020 | M/S. Padmavati Construction | 18 months | 52% | 53% | 184.15 (L) | 184.15 (L) | The contractor is instructed to complete the work with in March'23. | Initally, the work was delayed due to the execution of some additional works such as land developemnt, construction of retaining wall, heavy rain & COVID-19 etc. Presently, the work is in progress. |
Technical Education (Karimganj) | ||||||||||||||
1 | Establishment of 21 Nos. New Polytechnic in difference District of Assam under CSS during the year 2017-18 at Maizgram in Karimganj District. (Package No. Poly-13-CSS) | 4202-Capital-Outay on Education Sprots, Art & Culture-02-Technical Education-105-Engineering Technical Colleges and Institutes-0161-General-397-Polytechnic-13-Major works-99-others under SOPD-G during the 17-18 | PMA(H)/202/ 2016/463, dt.05.03.18 |
Rs.517.35074 (L) | 51201416.00 | GMC.37/ 2018/15, dt.19.12.18 | Abdul Matin | 18 (eighteen) months | 100% | 100% | Work completed . | |||
HIGHER EDUCATION (Karimganj District) | ||||||||||||||
1 | Construction of First floor of College Building (three storied foundation) at Karimganj College, Karimganj | ARUSHA/PIM/234/2019/1652 dt.11.06.2019 | 45.00 (L) | 32.06 (L) | SBC/CS/ 2021-22/08/ 360/405 dt.31.12.21 | Smti. Debjani Suklabaidya | 12 months | 100% | 100% | Work Completed & Handed over | ||||
WOMEN COLLEGE (KARIMGANJ) | ||||||||||||||
1 | Construction of 09 (nine) Nos. of New Model Women Colleges in the State of Assam at Karimganj | 4202-Capital Outlay on Education Sports Arts and Culture-01-General Education-203-University and Higher Education-2580-Establishment of 9 Women College-000-13-Major works-99-Others-SOPD-ODS voted during the year 2021-22 | AHE.944/2017/657 dt.10.06.2021 | 1873.07 (L) | 1768.47 (L) | SMC/21/2020/Pt/21 dt.20.08.21 | Sri. Ganesh Daimari | 24 months | 35.0% | 36.0% | As per survey report 25.88 bigha Land was handed over to the PWD Building on 29/11/2021 against the allotted land of 30 bigha 05 katha. Now, it is not possible to construct the boundary wall without receiving the balance land. As a result, the progrss of work is hampering badly. | |||
SIGNATURE PROJECT (KARIMGANJ DIST.) | ||||||||||||||
1 | Establishment of Pandit Deen Dayal Upadhaya Adarsha Mahavidyalaya at Ratabari LAC under Karimganj District under Signature Project for the year 2018-19, Package No. SP-42 | 4070-80-800-2333-000-13-99-SOPD-G | AA/PWB_ 2018-19(I)_98 dt.30.12.18 | Rs.10.00 (Cr.) | 98060323.00 | BPM.6/ 2019/7, dt.09.07.19 | Sri. Abdul Matin | 24 months | 62% | 63% | 508.57 (L) | 508.57 (L) | The contractor was instructed to expedite the work and should complete the work within March'23. | Initially, the work was delayed as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction of approach road to the site including other land development works. Also the work remain suspended for the several times during COVID-19.Presently Work is in progress. |
2 | Construction of Government Modern College at Bazaricherra at Patharkandi, Patharkandi LAC under Karimganj District under Signature Project for the year 2018-19, Package No.SP-43 | 4070-80-800-2333-000-13-99-SOPD-G | AA/PWB_ 2018-19(I)_99dt.30.12.18 | Rs.10.00 (Cr.) | 98061899.00 | BPM.103/ 2018/9 dt.14.06.2019 | Sri. Abdul Quddus | 24 months | 66.0% | 68.0% | 436.31 (L) | 436.31 (L) | On review meeting contractor instructed to expedite the work and should complete the work with in March'23. | Initially, the work was delayed as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction of approach road to the site including other land development works. Also the work remain suspended for the several times during COVID-19.Presently Work is in progress. |
COMMERCE STREAM (HIGHER EDUCATION) | ||||||||||||||
1 | Construction of 2 (two) Class rooms for Comerce Stream in each school for introduction of Comerce Stream in Karimganj Dist. during 2014-15 at- | PMA(S)199/ 2014/44, dt.07.03.15 |
45.66 (L) | 4566000.00 | SBC/CS/15-16/14/680, dt.02.11.15 |
Sri. Tahir Ahmed Khan | 120 days | It has been recomended to the higher authority for termination contract at contractor's own risk and cost on 03/09/2022. | The contractor has totally failed to execute the work and stopped the work since Oct. 2021 . Although several communication was made from this end but concerned contractor has not responded , also he rejected the Phone calls. | |||||
(i) Tukar Bazar High School, Karimganj South LAC, | 62% | 72% | ||||||||||||
(ii) Kaliganj Public H.S. School, Kaliganj, Karimganj, Badarpur LAC | 72% | 72% | ||||||||||||
(iii) Mahadev H.S. School, Rakesh Nagar, Karimganj, Badarpur LAC | 72% | 74% | ||||||||||||
EDUCATION DEPTT. (TEA GARDEN AREAS) (KARIMGANJ DISTRICT) | ||||||||||||||
1 | Construction of Model High School for Tea Garden Areas in Assam at - (Group No. TG-05) | |||||||||||||
(i) Pathni T.E. | 4059-01-051-2036-000-13-99-SOPD-G-V-GA for the FY 2020-21 | AA/PWB_ 2020-21(I)_ 1186 dt.08.10.2020 | 366.92419 (L) | 33798328.00 | BN/100/ 2020/14 dt.12.10.2020 | Abdul Matin | 12 months | 100% | 100% | 269.59 (L) | 269.59 (L) | Work completed & handed over |
||
(ii) Sephinjuribheel T.E. | 100% | 100% | Work completed & handed over |
|||||||||||
(iii) Bubrighat T.E. | 100% | 100% | Work completed & handed over |
|||||||||||
2 | Construction of Model High School for Tea Garden Areas in Assam at - (Category - II, Group No. TG-06) | |||||||||||||
(i) Dullavcherra T.E. at Damchera | 4059-01-051-2036-000-13-99-SOPD-G-V-GA for the FY 2020-21 | AA/PWB_ 2020-21(I)_ 1188 dt.08.10.2020 | 225.04524 (L) | 20594507.00 | BN/74/ 2020/23 dt.23.11.2020 | Md. Junel Hussain | 10 (ten) months | 100% | 100% | 163.98 (L) | 205.907 (L) | Work completed & handed over |
||
(ii) Goombhira T.E. in Karimganj Dist. | 100% | 100% | Work completed & handed over |
|||||||||||
3 | Construction of 4(Four) nos. of additional classroom, Laboratory, Kitchen, Toilet Block and cycle stand of model Tea garden School at- | |||||||||||||
(i) Pathni T.E. , Karimganj District. (Gr. I) | 4059-01-051-2036-000-13-99-SOPD-G-V-GA | AA/PWB_ 2022-23(I)_ 1412 dt.17.08.2022 | 61.06400 (L) | 5815608.39 | SBC/CS/ 2022-23/05/456/Gr -I/516 dt.29.10.2022 | Abdul Matin | 12 (twelve) months | 0% | 0% | The Contractor is requested to start the work immediately | Work yet to be started by the Contractor. | |||
(ii) Sephinjuribheel T.E. , Karimganj District. (Gr. II) | 4059-01-051-2036-000-13-99-SOPD-G-V-GA | AA/PWB_ 2022-23(I)_ 1413 dt.17.08.2022 | 61.06400 (L) | 5815608.39 | SBC/CS/ 2022-23/05/456/Gr -II/517 dt.29.10.2022 | Abdul Matin | 12 (twelve) months | 0% | 0% | |||||
(iii) Bubrighat T.E. , Karimganj District. (Gr. III) | 4059-01-051-2036-000-13-99-SOPD-G-V-GA | AA/PWB_ 2022-23(I)_ 1414 dt.17.08.2022 | 61.06400 (L) | 5815608.39 | SBC/CS/ 2022-23/05/456/Gr -III/518 dt.29.10.2022 | Abdul Matin | 12 (twelve) months | 0% | 0% | |||||
(iv) Dullavcherra T.E. at Damchera , Karimganj District. (Gr. V) | 4059-01-051-2036-000-13-99-SOPD-G-V-GA | AA/PWB_ 2022-23(I)_ 1415 dt.17.08.2022 | 61.06400 (L) | 5810000.00 | SBC/CS/ 2022-23/05/456/Gr -V/459 dt.10.10.2022 | Sri Sourav Das | 12 (twelve) months | 0% | 0% | |||||
(v) Goombhira T.E., Karimganj District. (Gr. IV) | 4059-01-051-2036-000-13-99-SOPD-G-V-GA | AA/PWB_ 2022-23(I)_ 1416 dt.17.08.2022 | 61.06400 (L) | 5810000.00 | SBC/CS/ 2022-23/05/456/Gr -IV/494 dt.29.10.2022 | Sri Sourav Goswami | 12 (twelve) months | 0% | 0% | |||||
UNDER M.S.D.P. MRS (KARIMGANJ DIST.) | ||||||||||||||
1 | Construction of Model Residential School Building under MSDP at Ramkrishna Nagar, Karimganj, Package No. MRS/18 | 2575-Other Special Areas Programme-02-Backward Areas-800-Others Expenditure-2919-Multi-Sectoral Development Programme for Minorities in selected Minority Concerned Districts-092-35-Grants for creation of Capital Assets-99-Others (Central Share-CSS) during 2017-18 under Grant No. 42 | WMD-18012/2/2018-WMD(Part)/9 dt.17.03.18 | Rs.3042.69 (L) | 288110126.00 | BPM.45/ 2019/10 dt.09.07.19 | M/S. Tribeni Construction Ltd. | 24 months | 58.0% | 60.0% | 1334.57 (L) | 1334.57 (L) | The Contractor is instructed to maintain the slope with temporary protection work such as Bamboo palasiding etc. However, revised estimate incorporating RCC Retaining wall in most vulnerable portion of slope has been sent to the C.E. PWD Building for approval. | Initially, the work was delayed as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction for approach road to the site including other land development works. Moreover it invariably required to provide immediate slope protection work before taking up further construction work. Also till date final demarcation is not done yet by the R.K. Nagar Circle Office and the work remain suspended for the several times during COVID-19. . Presently Work is in progress. |
MSDP (I.T.I. in Karimganj District) | ||||||||||||||
1 | Construction of Proposed I.T.I. at Eraligool in Karimganj District for the year - 2012-13 | 2575-other Spl. Areas Programmee-02-Backward areas-001-Direction & Admn-III-Centrally Sponsoured Scheme-2919-Implementation Dev. Scheme in Minority Concentrated Dist. under Multi Sectorial Dev. Programmee-35-Grant-in-aid (Capital Assets) during 2013-14 | WMD.155/ 2013/7 dt.22.08.2013 |
Rs.429.70 (L) | 376.112 (L) | PWO No. BPM.48/ 2012/20 dt.28.02.14 |
Sri Abdul Quddus | 12 months | 70.5% | 70.5% | 260.00 (L) | 260.00 (L) | Deputy Commissioner Karimganj is requested to provide a suitable land for construction of Girls Hostel so as to complete the balance work. | All the works such as administrative building, Grade-IV Qtr. etc. are completed except Girls Hostel due to non availability of land. As such work was withdrown by C.E. PWD Building. |
MSDP (Girls Hostel in Karimganj District) | ||||||||||||||
1 | Construction of 100 bedded Girls Hostel at (i) Shah Badaruddin High School, Badarpur (ii) Bhanga H.S. School, Bhanga under MSDP in Karimganj District. | 2575-other Spl. Areas Programmee-02-Backward areas-001-Direction & Admn-III-Centrally Sponsoured Scheme-2919-Implemented Dev. Scheme in Minority Concentrated Dist. under Multi Sectorial Dev. Programmee-35-Grant-in-aid (Capital Assets) during 2013-14 | WMD.68/ 2013/31 dt.18.06.2013 |
Rs.316.00 (L) | 302.69 (L) | BPM.63/ 2013/8 dt.24.10.13 |
M/S. J.J. Construction | 12 months | 27% | 27% | 81.00 (L) | 81.00 (L) | It has been recomended to the higher authority for termination contract at contractor's own risk and cost. | Contractor prayed for withdrow the work. |
UNDER M.S.D.P. 12th PLAN (KARIMGANJ DIST.) | ||||||||||||||
1 | Construction of RCC Delivery Room with Neonatal Room at Kaliganj Hospital under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.20.00 (L) | 1980189.00 | SBC/CS/ 2017-18/17/525, dt.14.03.18 |
Sri. Fajal Hussain | 6 months | 40% | 45% | As per the review meeting the concerned Contractor committed to complete the work within Dec'2022. | The Contractor has been delaying the wok since inspection. As such notice has been served to the contractor by imposing liquidity damage. | |||
2 | Construction of PHC Building at Nagrabazar under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.62.48 (L) | 6184941.60 | SBC/CS/ 2017-18/16/418/Gr.-V/547, dt.19.03.18 |
M/S. S.Y. Const. | 18 months | 100% | 100% | 31.26 (L) | 31.26 (L) | Work completed . | ||
3 | Construction of PHC Building at Kurtikuchi under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.62.48 (L) | 6185506.20 | SBC/CS/ 2017-18/16/418/Gr.-III/551, dt.19.03.18 |
M/S. S.Y. Const. | 18 months | 100% | 100% | 31.24 (L) | 31.24 (L) | Work completed & handed over |
||
4 | Construction of Building at Makunda Chiristian Hospital under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.50.00 (L) | 4890684.36 | SBC/CS/ 2017-18/16/418/Gr.-IV/548, dt.19.03.18 |
Sri. Monish Das | 18 months | 100% | 100% | 25.00 (L) | 25.00 (L) | Work completed & handed over |
||
5 | Construction of Girls Hostel (50 bedded) at Patharkandi College, Vill-Rajbari under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.78.00 (L) | 7662455.65 | SBC/CS/ 2017-18/16/418/Gr.-I/549, dt.19.03.18 |
M/S. S.Y. Const. | 18 months | 99% | 99% | 38.05 | 38.05 | Notice issued to the Contractor has been instructed to complete the work within Dec'2022. | Civil work almost complete. However electrical work was kept pending by the contractor since long. Recently the contractor has started the electrical work. | |
6 | Construction of RCC Hospital Building at Bhanga as per NRHM norms under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.50.00 (L) | 4931000.00 | SBC/CS/ 2018-19/08/305, dt.26.12.18 |
Fazal Hussain | 10 months | 81% | 81% | 25.00 (L) | 25.00 (L) | Notice issued to the Contractor has been instructed to complete the work within Dec'2022. | In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Oct'22. | |
7 | Construction of CHC at Badarpur under MSDP 12th Plan | WMD.46/ 2016/25, dt.09.03.17 |
Rs.25.51 (L) | 2515554.58 | SBC/CS/ 2018-19/03/ 120/178, dt.21.09.18 |
Sri. Fazal Hussain | 6 months | 50% | 55% | Notice issued to the Contractor has been instructed to complete the work within Dec'2022. | In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Nov'22. | |||
8 | Construction of Medical Sub-Centre at Bazarghat Sub-Centre as per NRHM norms in Dullavcherra Deb. Block Karimganj under MSDP 12th Plan for the year 2016-17 (Group No. II) | WMD.46/ 2016/25, dt.09.03.17 |
Rs.14.75 (L) | 1460396.00 | SBC/CS/2017-18/17/527 dt.14.03.18 |
Sri. Taher Ahmed Siddiquey | 6 months | 90.0% | 91.0% | 7.37 (L) | 7.37 (L) | Notice issued to the Contractor has been instructed to complete the work within Dec. '2022. | In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Aug'22. | |
9 | Construction of PHC Building at Balia Bazar under MSDP 12th Plan in Karimganj Dist. | 8018719.00 | SBC/CS/ 2019-20/14/ 318/393 dt.20.01.20 |
Sri. Shahid Ahmed Tapader | 18 months | 42% | 42% | 33.50 (L) | 33.50 (L) | Balance work estimate under preparation. | Work withdrawn. Balanced work estimate will be submitted soon. | |||
10 | Construction of School Building of Balipipla High School under PMJVK (MSDP) 12th Plan in Karimganj Dist. | WMD.75/2017/7 dt.07.03.2017 | 5000000 | 4937997.00 | SBC/CS/ 2021-22/06/399 dt.29.12.21 |
M/S. AKECON INDIA | 12 months | 55% | 60% | Work is in progress | ||||
Health Deptt. ( Karimganj District ) | ||||||||||||||
1 | Upgradation of 24 Nos. of existing Hospitals for setting up of ICU's for treatment of patents of COVID-19 under Assam Critical Care project 2020 at Karimganj (Package No. DIS-COV-19/21) | 4210-Co. on M&HP-03-MET&R-001-Direction & Admn.-0172-HQ Estt-070-COVID-19-13-Major works-99-Others under CSS (NESIDS) for the FY 2020-21 | HLB.149/2020/Pt/446 dt.08.10.2020 | 15789.31 (L) | 51658665.00 | GMC.40/2020/21 dt.13.11.2020 | Sri. Abdul Matin | 4 (four) months | 95% | 95% | Contractor is instructed resume the work immediately and to complete the balance work with in Dec'22. | ICU Unit work completed & handed over. However other ancillary works are kept pending by the contractor due to non receipt of any payment against the work done so far. | ||
2 | Establishment of 42 bedded Dedicated care Unit (30 o2 Supported beds + 8HDU + 4 PICU) in Karimganj District. (Gr.-IV) | NHM-32048/3/ 2021/Construction-NHM/58 Dt.20.01.2022 | Rs. 85,80,763.00 | Rs. 84,09,147.74 | SBC/CS/2021-22/09/376/ Gr-IV/90 dt.01.01.2022 |
Nasim Uddin Ahmed | 3 months | 71% | 75% | A notice has been served to the contractor to complete the work with in Sept'22. | Initially,Work was delayed due to delay in handing over of site. Presently, the work is in progress. | |||
3 | Establishment of RT PCR Laboratory in Karimganj District. (Gr.-V) | NHM-32048/3/ 2021/Construction-NHM/58 Dt.20.01.2022 | Rs. 11,98,430.00 | Rs. 11,74,461.40 | SBC/CS/2021-22/09/376/Gr-V/69 dt.24.01.2022 | Biplab Banik | 3 months | 100% | 100% | Work Completed | ||||
4 | Design, Supply, Installation & Commissioning of 10KL Cryogenic Tank, MGPS and other support system at Civil Hospital in Karimganj District for the dedicated 32/42 bedded Pediatric care unit . (Gr.-II) | No. NHM-32048/3/2021/Construction-NHM/58 Dt.20.01.2022 | Rs. 80,00,000.00 | Rs. 70,40,000.00 | SBC/CS/2021-22/10/403/85/ Gr-II/143 dt.28.02.2022 |
M/S AKECON INDIA, Prop:- Equbal Uddin | 3 months | 15% | 15% | Drawing for Oxygen tank received on 28th Sept'2022. | Work is in progress. | |||
EVMs & VVPATs (KARIMGANJ DIST.) | ||||||||||||||
1 | Construction of Godowns/Warehouse for proper storage of EVMs & VVPATs in the 50 Election Districts of Assam for the year 2017-18 (DEO Karimganj) | 4059-60-Other Bldgs.-051-Constn.-2286-Constn. Of warehouse for EVM-000-13-Major works-99-others-SOPD-G-GA-KN/NN/BN-V during 2017-18 | ELA.36/2015/321, dt.26.03.2018 | Rs.218.13 (L) | 20447166.00 | PWO No. CS/T/BD/ 06/2018/6, dt.23.05.18 | Sri. Abdul Quddus | 7 (Seven) months | 65% | 75% | An updated work programme has been submitted to D.C. Karimganj with a period completion, due to delay in handing over of site, heavy rain in the month of May, June, July'22. | Initially, the contractor could not started the work due to unexpected long time delay of 3 & 1/2 years in handing over of site. However work was started on last week of January'22 and presently, work is in progress. | ||
MINI STADIUM | ||||||||||||||
1 | Construction of Mini Stadium at Ramkrishna Nagar under Ratabari LAC, (District-Karimganj), Assam. | 12,10,77,142.00 | CS/T/TB-I/40/2022/18 dt. 31/10/2022. |
Abdul Bachit | 18 months | 1% | 1.5% | Work is in progress | ||||||
2 | Construction of Mini Stadium at Uttar Sepenjuri, Patherkandi LAC, (District-Karimganj), Assam. | 4059-60-051-4548-000-13-99-SOPD-G-V-GA | AA/PWB_2022-23(I)_1535 | 1268.97484(L) | 12,10,94,909.00 | CS/T/TB-I/35/2022/12 dt. 04/11/2022. |
Abdul Quddus | 18 months | 1% | 1.5% | Work is in progress | |||
4059-60-051-5247-252-05-03-SOPD-G-V-GA | 38.32116(L) | |||||||||||||
Total=1307.296(L) | ||||||||||||||
District Science Centre (Karimganj Dist.) | ||||||||||||||
1 | Land development and Construction of boundary wall for Karimganj Distric Science Centre | STE.76/2018/Pt-V/34 dt.29.11.2018 | 239.70 (L) | SBC/CS/2011-22/04/282/336 dt.09.11.21 | M/S. Shristy Enterprise | District Scince centre is requested to handover encumbrance free site to PWD Building to start the construction of the said work. Also Circle officer, Karimganj also requested to make the site encrochment free. | The Director of ASTE Council instructed to PWD Building not to start any work as the plot of land is now under subjudice with the Misc.Case No. 449/2021 arising out of T.S. No.485/2021(Bakul Nath and other VS. The state of Assam & Others ). | |||||||
2 | Construction of Eleven (11) Nos. of District Science Centre at Karimganj, Package No. GMC-11 Nos. DSC | 5425-00-800-3103-600-13-99-SOPD-G-V-GA | AA/ST_2019-20(I)_07 dt.27.11.19 | 15042.84 | 822.77 (L) | GMC.8/2020/43 dt.03.06.21 | M/S. North East Plantation & Commercial Pvt. Ltd. | |||||||
District Jail Karimganj | ||||||||||||||
1 | Construction of Double storied administration office building with prisoner interview room go down, doctor's chamber with at least 10 (Ten) bedded hospital at district jail, Karimganj. | AA/PRI_2020-21(I)_111 Dt. 10/09/2022. | 147.82(L) | 144.74(L) | SBC/CS/ 2020-21/04/210/322 dt. 17/12/2020. |
Sri Harihar Deka | 18 months | The Superintendent of Jail is reaquested to provide NOC from the Jail authority to start the said work as well as to ensure proper security arrangement during construction vide T.O.Dt. 01/09/2022. | The work could not be started due to non receipt of NOC from the Jail authority. | |||||
B.A.D.P. ( Karimganj District ) | ||||||||||||||
1 | Construction of old Tourist Centre at Historical Malegarh Crematorium for Rs.40.00 lacs under BADP 2019-20 of Karimganj district | AA/DBA_2020-21(I)_512 dt.18.11.2020 | 40.00 (L) | 3951519.00 | SBD/TB/CS/ 2020-21/ 19/272 dt.25.02.21 | Sri. Ratnadeep Das Purkayastha | 6 months | 65% | 95% | Notice served to the contractor on 09/08/2022 to expedite the work and complete the work within Dec'2022. | Initially,Work was delayed due to delay in handing over of site. Presently Work is in progress | |||
2 | Construction of BOP Camp at Choto Bubirbond | 4575-02-001-0678-000-13-01-SOPD-ODS-V-GA” for the financial year 2021-22 | AA/DBA_2021-22(I)_684 dt.11.08.2021 | 44.99 (L) | 44,56,349.00 | SBD/TB/ CS/2021-22/04/140 dt.01.10.21 | Samsul Haque Choudhury | 6 Months | Contractor was instructed to start the work immediatly and complete the work within 31.12.2022. | Initially,Work was delayed due to delay in handing over of site. Now, the site has been handed over to the contractor in last month and he is instructed to start the work immediately. | ||||
3 | Construction of Ratabari Anchalik Nadwa Office in Karimganj Dist. under DCP for Development of Inter-State Border area during 2013-14 (Group-A) | 297000.00 | SBD/TB/ CS/14-15/ 10/1061 Dt.28.01.15 |
Sri. Tahir Ahmed Khan | 45 days | 70% | 70% | It has been recomended to the higher authority for termination contract at contractor's own risk and cost. | The contractor has totally failed to execute the work and stopped the work since Oct. 2021 . Although several communication was made from this end but concerned contractor has not responded , also he rejected the Phone calls. | |||||
4 | Construction of Open Community Hall (Assam type) at Solgai T.E. under Indo-Bangladesh Border Area under Lowairpoa Block at Karimganj District under BADP (SCA) for the year 2015-16 (Group No. II) | 1287000.00 | SBC/CS/ 2016-17/ 11/457, dt.27.03.17 |
Sri. Debjani Das Roy | 90 days | 0% | 0% | Work already withdrown. | The work was withdrawn as no work was done by the contractor. Revised estimate submitted to D.C. Karimganj on 18.06.2020 for approval. | |||||
5 | Construction of Community Hall near Pallimangal Club at Patharkandi under Interest accrued against BADP Fund in Karimganj District (Group No. I) | DBPD.94/2018/ BADP/108 dt.05.03.2019 | 10.00 (L) | 984400.00 | SBD/TB/CS/ 2019-20/1/2705 dt.09.08.19 |
Sri. Sushanta Sekhar Paul | 90 days | 0% | 0% | It has been recomended to the higher authority for termination contract at contractor's own risk and cost. | Contractor has not yet started any work and now he has prayed for withdraw the work due to obstruction of public & price hike of the materials & labour | |||
UNDER 13TH FINANCE COMMISSION (B.A.D.P.) (Karimganj Dist.) | ||||||||||||||
1 | Construction of Community Hall under Thirteen Finance Commission in Karimganj District of Indo-Bangla Boarder for 2011-12 (Gr-A) | DBA.230/2011/5 dt.4.1.12 | 4000000.00 | 3960109.00 | SBC/CS/11-12/58/905, dt.18.1.12 | Sri. Paresh Chandra Ghosh | 2 ( two ) months | 80% & 65% | 80% & 65% | 20.00 | 20.00 | It has been recomended to the higher authority for termination contract at contractor's own risk and cost. | Penalty imposed | |
Jerjeri G.P - 2 Nos. | ||||||||||||||
Dengarbond G.P - 2 Nos. | 100% & 100% | 100% & 100% | ||||||||||||
Balipipla G.P | 55% | 55% | ||||||||||||
Lowairpoa G.P - 2 Nos. | 75% & 100% | 75% & 100% | ||||||||||||
CM's Special Package for Barak Valley during 2013-14 (Karimganj Dist.) | ||||||||||||||
1 | Upgradation of SC/SD/PHC to Community Hall Centre (Phase-I) in Barak Valley under CM's Special Package at R K Nagar CHC in Karimganj District under Annual Plan 2013-14 | 4210-Co-on-Medical & PH-01-Urban Health-Service-001-Direction & Admn.-172-HQ-Estt. (ii) CM's Spl. Package for Barak Valley-543-works-13 Major work Plan General for 13-14 |
HLA.130/ 2014/93 Dt.01.03.2014 |
Rs.330.00 (L) | 314.69 (L) | GMC.32/ 2014/20 Dt.04.03.15 |
Sri. Abdul Quddus | 18 (eighteen) months | 95% | 98% | 60.697(L) | 60.697(L) | 80% payment against the executed work is pending since March 2015. However, the contractor has committed to complete the work within November '2022. | Work is in progress |
2 | Cosntruction of Swimming Pool in Karimganj Dist. under CM's Special Package for Barak Valley for the year 2014-15 | No. DB(B)/19/ 2013/Pt-I/13 Dt.24.02.15 |
Rs.2.00 Crore | 19660000.00 | BN/06/2015/37 Dt.25.01.16 |
Sri. Iftakur Rahman | 12 months | 97% | 97% | 166.75 (L) | 166.75 (L) | Civil works completed in Feb. 2022 and electrical work is in progress. The contractor committed to complete the work within November 2022. | Work is in progress | |
3 | Construction of Market Complex and Pucca Drain in and around the Bazar area for letting out dead water at Kaliganj Bazar | 4059-01-office-Building-101-Constn. Gen. Pool Accomodation-0121-Building (PW)-462-Cms Spl. Package for Barak Valley -13-Major works-99-others-state share, SOPD-G during the year 2017-18 | DB(B).19/2013/12 Dt.11.11.13 Revised A.A. No.DB(B).101/ 2017/Pt-I/20 Dt.31.7.17 |
Rs.245.76 (L) | 24310731.00 | BN/144/ 2013/14 Dt.15.02.14 |
M/S. J & J Const. | 10 (ten) months | 80% | 80% | 140.543 (L) | 140.543 (L) | It has been recomended to the higher authority for termination contract at contractor's own risk and cost . | Contractor prayed for withdrawal of the work. |
4 | Construction of Market Complex and Pucca Drain at Anglar Bazar in Karimganj District | DB(B).19/2013/13 Dt.11.11.13 | Rs.200.00 (L) | 19707727.00 | BN/145/ 2013/13 dt.15.02.14 | Mujibur Rahman | 10 (ten) months | 30% | 30% | 55.09 (L) | 55.09 (L) | It has been recomended to the higher authority for termination contract without penalty . | The concerned contractor is not willing to do the remaining work as the land is subjudiced for last five years | |
5 | Construction of Mini Stadium at Marjatkandi Public Higher Secondary School in Karimganj District under CM's Special Package for Barak Valley during 14-15 | DB(B).19/ 2013/Pt/11 Dt.24.02.15 Revised A.A. No.DB(B).101/ 2017/Pt-I/21 Dt.31.7.17 |
Rs.1.00 Crore | 9896825.00 | BN/04/ 2015/10 dt.10.04.15 | M/S. J&J Construction | 9 (nine) months | 50% | 50% | 50.04 (L) | 50.04 (L) | It has been recomended to the higher authority for termination contract at contractor's own risk and cost . | Contractor prayed for withdrawal of the work. | |
6 | Construction of RCC Community Hall with Library at Marjatkandi and RCC Community Hall at Chandrapur Bagbari, Gilaijan and RCC Guest House at Kuchilargool in Karimganj District under CM's Special Package for Barak Valley for the year 2014-15 | 4059-01-office-Building-101-Constn. Gen. Pool Accomodation-0121-Building (PW)-462-Cms Spl. Package for Barak Valley -13-Major works-99-others-state share SOPD-G during the year 2017-18 | DB(B).19/ 2013/Pt-I/17 Dt.24.02.15 Revised A.A. No.DB(B).101/ 2017/Pt-I/19 Dt.31.7.17 |
Rs.1.00 Crore | 98.28 (L) | BN/10/ 2015/11 Dt.02.05.15 |
M/S. J&J Construction | 82% | 82% | It has been recomended to the higher authority for termination contract at contractor's own risk and cost . | Contractor prayed for withdrawal of the work. | |||
7 | Construction of 100 bedded Multistoried Boys Hostel at Kaliganj in Karimganj District under CM's Special Package for Barak Valley (Phase-II) for the year 14-15 | DB(B).19/ 2013/Pt-I/10 Dt.24.02.15 Revised A.A. No.DB(B).101/ 2017/Pt-I/18 Dt.31.7.17 |
Rs.2.00 Crore | 197.38 (L) | BN/03/ 2015/13 Dt.10.04.15 |
M/S. J&J Construction | 54% | 54% | 84.191 (L) | 84.191 (L) | It has been recomended to the higher authority for termination contract at contractor's own risk and cost . | Contractor prayed for withdrawal of the work. | ||
8 | Construction of Swasan at Maizgram & Beautification of Town Idgah, Swahid Bedi & Emersion Ghat & Community Hall etc. in Karimganj Dist. under CM's Special Package for Barak Valley for the year 2014-15 | DB(B).19/ 2013/Pt-I/24 Dt.03.03.15 Revised A.A. No.DB(B).101/ 2017/Pt/2 Dt.31.7.17 |
Rs.550.00(L) | 52700000.00 | FWO No. BN/09/2015/30 Dt.29.12.15 |
M/S. Modern Construction Co. | 12 months | 23% | 23% | Intend to Termination of Contact - Notice was served on 08/08/2022 at contractor's own risk and cost . | The concerned contractor is not willing to do the remaining work. Also the completion time of the work has already been expired. | |||
UNTIED FUND in Karimganj District | ||||||||||||||
1 | Construction of Bishnupriya Manipuri Community Hall at Patharkandi in Karimganj Dist. under Untied Fund for 2016-17 (Gr. No. 2) | No. KDP.263/UF/ 2016-17/65, dt.15.06.2017 |
100.00 (L) | 9746347.00 | No. SBC/CS/ 2017-18/05/195 dt.05.08.17 |
Sri. Bimal Sinha | 90 days | 90% | 98% | 50.94 (L) | 50.94 (L) | Final Notice served to complete the work within Dec 2022. | Civil works were completed six months ago. Only electrical transformer installation work is pending, which is now under progress. | |
2 | Construction of Swami Vivekananda Audtorium and Guest House near Swami Vivekananda, Sonakhira, Patharkandi under Untied Fund for 2017-18 (Gr. No.II) | No.PD/DCP/30/ 2018/73 Dt.04.08.2018 | 7000000.00 | 6935177.00 | No. SBC/CS/ 2018-19/ 07/190/375 dt.01.02.19 | Sri. Bimal Sinha | 12 Months | 99% | 100% | 47.89 (L) | 47.89 (L) | Finall Bill submitted | Work completed and handed over | |
REVENUE DEPTT. (Karimganj Dist.) | ||||||||||||||
1 | Construction of Circle Office building including Civil, Electrical works and brick boundary wall with Iron gate in respect of Circle Officer, Nilambazar Revenue Circle under Karimganj District | 4059-01-051-0408-Revenue Deptt. 701-Const. of Circle Officer etc.-13 Major works-99-Non-Plan during year 2015-16 | RRA.69/2014/42 dt.13.05.15 |
16696367.00 | 14079424.00 | FWO No. BN/69/ 2014/14 Dt.18.03.15 |
Sri. Mojibur Rahman | 12 months | 70.5% | 70.5% | 39.96 (L) | 39.96 (L) | It has been recomended to the higher authority for termination contract . | Main Office Building work completed & handed over. However boundary wall is not done by the contractor due to non receipt any payment against the pending bills of the contractor since 2018 and now the Contractor is not willing to any work due to price hike. |
-Do- Soil Testing work | 60000.00 | Creative Engineers | 100% | 100% | 60000.00 | 60000.00 | Final payment made | |||||||
,Executive Engineer P.W.D. | ||||||||||||||
Karimganj District Territorial Building Division, | ||||||||||||||
Karimganj | ||||||||||||||