PWD Buildings

Last Updated on: February 08, 2023

INTRODUCTION


The Assam Public Works Department was established in the year 1880. The department has undergone considerable expansion since after attainment of independence and for smooth functioning of the organization, to share the increasing work load and for providing more stress to development works, the Assam P.W.D. has been divided into two wings viz. Roads and Building wings in August 1977 and since then  both the wings are functioning with their prescribed identity. The principal function of the Public Works Department is to develop the infra-structure for transport & communications of the State. Assam P.W.D. discharges its function in construction and repair of roads, bridges, culverts in the state including construction and repair of public buildings of the state and till date it has reached a considerable height of fame and competence.

Public Works Department(Building Wing) deals with the construction, maintenance and repair of Government Buildings and structures in the state of Assam and also outside Assam for construction of Assam Bhawan etc.

Key Functions:- 

(i) Construction, repair and maintenance of various Government and residential building of the State.

(ii) Adoption and implementation of the latest standards, State of the Art practices, use of innovative and appropriate technology and building materials to enhance quality, productivity and affordability.

 

PROGRESS REPORT FOR THE MONTH OF DECEMBER '2022 OF KARIMGANJ DISTRICT UNDER KARIMGANJ DISTRICT TERRITORIAL BUILDING DIVISION, KARIMGANJ
Sl. No. Name of Project / Works Head of Account A.A  No. and Date  A/A Amount  Tender Value (Rs) Formal work order and Date Name of contractor Date of completion as per FWO Up to date Physical Progress of Civil & Electrical works (in%) Financial Progress of Civil & Electrical works(in Lakhs/%) Action taken against defaulting contractors with details. Remarks 
Previous month Dec '22 Previous month Dec.'22
  CULTURAL DEPTT. (Karimganj Dist.)            
1 Construction of 1000 capacity Auditorium at R.K. Nagar, Karimganj, Assam 4059-01-101-0121-227-13-99-SOPD-G-V-GA AA/PWB_2020-21(I)_1134 dt.17.09.2020 Rs.1390.04800 (L) 92086724.00 ADP/49/ 2019/24 dt.19.10.2020 M/S. Padmavati Construction 18 months 52% 53% 184.15 (L) 184.15 (L) The contractor is instructed to complete the work with in March'23. Initally, the work was delayed due to the execution of some additional works such as land developemnt, construction of retaining wall, heavy rain & COVID-19 etc. Presently, the work is in progress.
  Technical Education (Karimganj)                    
1 Establishment of 21 Nos. New Polytechnic in difference District of Assam under CSS during the year 2017-18 at Maizgram in Karimganj District. (Package No. Poly-13-CSS) 4202-Capital-Outay on Education Sprots, Art & Culture-02-Technical Education-105-Engineering Technical Colleges and Institutes-0161-General-397-Polytechnic-13-Major works-99-others under SOPD-G during the 17-18 PMA(H)/202/
2016/463, dt.05.03.18
Rs.517.35074 (L) 51201416.00 GMC.37/ 2018/15, dt.19.12.18 Abdul Matin 18 (eighteen) months 100% 100%       Work completed .
  HIGHER EDUCATION (Karimganj District)                    
1 Construction of First floor of College Building (three storied  foundation) at Karimganj College, Karimganj   ARUSHA/PIM/234/2019/1652 dt.11.06.2019 45.00 (L) 32.06 (L) SBC/CS/ 2021-22/08/ 360/405 dt.31.12.21 Smti. Debjani Suklabaidya 12 months 100% 100%       Work Completed & Handed over
  WOMEN COLLEGE (KARIMGANJ)                  
1 Construction of 09 (nine) Nos. of New Model Women Colleges in the State of Assam at Karimganj 4202-Capital Outlay on Education Sports Arts and Culture-01-General Education-203-University and Higher Education-2580-Establishment of 9 Women College-000-13-Major works-99-Others-SOPD-ODS voted during the year 2021-22 AHE.944/2017/657 dt.10.06.2021 1873.07 (L) 1768.47 (L) SMC/21/2020/Pt/21 dt.20.08.21 Sri. Ganesh Daimari 24 months 35.0% 36.0%       As per survey report 25.88 bigha Land was handed over to the PWD Building on 29/11/2021 against the allotted land of 30 bigha 05 katha. Now, it is not possible to  construct the boundary wall without receiving the balance land. As a result, the progrss of work is hampering badly.
  SIGNATURE PROJECT (KARIMGANJ DIST.)            
1 Establishment of Pandit Deen Dayal Upadhaya Adarsha Mahavidyalaya at Ratabari LAC under Karimganj District under Signature Project for the year 2018-19, Package No. SP-42 4070-80-800-2333-000-13-99-SOPD-G AA/PWB_ 2018-19(I)_98 dt.30.12.18 Rs.10.00 (Cr.) 98060323.00 BPM.6/ 2019/7, dt.09.07.19 Sri. Abdul Matin 24 months 62% 63% 508.57 (L) 508.57 (L) The contractor was instructed to expedite the work and should complete the work within March'23. Initially, the work was delayed  as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction of approach road to the site including other land development works. Also the work remain suspended for the several times during COVID-19.Presently Work is in progress.
2 Construction of Government Modern College at Bazaricherra at Patharkandi, Patharkandi LAC under Karimganj District under Signature Project for the year 2018-19, Package No.SP-43 4070-80-800-2333-000-13-99-SOPD-G AA/PWB_ 2018-19(I)_99dt.30.12.18 Rs.10.00 (Cr.) 98061899.00 BPM.103/ 2018/9 dt.14.06.2019 Sri. Abdul Quddus 24 months 66.0% 68.0% 436.31 (L) 436.31 (L) On review meeting contractor instructed to expedite the work and should complete the work with in March'23. Initially, the work was delayed  as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction of approach road to the site including other land development works. Also the work remain suspended for the several times during COVID-19.Presently Work is in progress.
  COMMERCE STREAM (HIGHER EDUCATION)                    
1 Construction of 2 (two) Class rooms for Comerce Stream in each school for introduction of Comerce Stream in Karimganj Dist. during 2014-15 at-   PMA(S)199/
2014/44, dt.07.03.15
45.66 (L) 4566000.00 SBC/CS/15-16/14/680,
dt.02.11.15
Sri. Tahir Ahmed Khan 120 days         It has been recomended to the higher authority for termination contract at contractor's own risk and cost on 03/09/2022. The contractor has totally failed to execute the work and stopped the work since Oct. 2021 . Although several communication was made from this end but concerned contractor has not responded , also he rejected  the Phone calls. 
  (i) Tukar Bazar High School, Karimganj South LAC,   62% 72%    
  (ii) Kaliganj Public H.S. School, Kaliganj, Karimganj, Badarpur LAC   72% 72%    
  (iii) Mahadev H.S. School, Rakesh Nagar, Karimganj, Badarpur LAC   72% 74%    
  EDUCATION DEPTT. (TEA GARDEN AREAS) (KARIMGANJ DISTRICT)                  
1 Construction of Model High School for Tea Garden Areas in Assam at - (Group No. TG-05)                          
  (i) Pathni T.E. 4059-01-051-2036-000-13-99-SOPD-G-V-GA for the FY 2020-21 AA/PWB_ 2020-21(I)_ 1186 dt.08.10.2020 366.92419 (L) 33798328.00 BN/100/ 2020/14 dt.12.10.2020 Abdul Matin 12 months 100% 100% 269.59 (L) 269.59 (L) Work completed &
handed over
  (ii) Sephinjuribheel T.E. 100% 100% Work completed &
handed over
  (iii) Bubrighat T.E. 100% 100% Work completed &
handed over
2 Construction of Model High School for Tea Garden Areas in Assam at - (Category - II, Group No. TG-06)                          
  (i) Dullavcherra T.E. at Damchera 4059-01-051-2036-000-13-99-SOPD-G-V-GA for the FY 2020-21 AA/PWB_ 2020-21(I)_ 1188 dt.08.10.2020 225.04524 (L) 20594507.00 BN/74/ 2020/23 dt.23.11.2020 Md. Junel Hussain 10 (ten) months 100% 100% 163.98 (L) 205.907 (L) Work completed &
handed over
  (ii) Goombhira T.E. in Karimganj Dist. 100% 100% Work completed &
handed over
3 Construction of 4(Four) nos. of additional classroom, Laboratory, Kitchen, Toilet Block and cycle stand of model Tea garden School  at-                          
  (i) Pathni T.E. , Karimganj District. (Gr. I)  4059-01-051-2036-000-13-99-SOPD-G-V-GA AA/PWB_ 2022-23(I)_ 1412 dt.17.08.2022 61.06400 (L) 5815608.39 SBC/CS/ 2022-23/05/456/Gr -I/516 dt.29.10.2022 Abdul Matin 12 (twelve) months 0% 0%     The Contractor is requested to start the work immediately Work yet to be started by the Contractor.
  (ii) Sephinjuribheel T.E. , Karimganj District. (Gr. II)  4059-01-051-2036-000-13-99-SOPD-G-V-GA AA/PWB_ 2022-23(I)_ 1413 dt.17.08.2022 61.06400 (L) 5815608.39 SBC/CS/ 2022-23/05/456/Gr -II/517 dt.29.10.2022 Abdul Matin 12 (twelve) months 0% 0%    
  (iii) Bubrighat T.E.  , Karimganj District. (Gr. III)  4059-01-051-2036-000-13-99-SOPD-G-V-GA AA/PWB_ 2022-23(I)_ 1414 dt.17.08.2022 61.06400 (L) 5815608.39 SBC/CS/ 2022-23/05/456/Gr -III/518 dt.29.10.2022 Abdul Matin 12 (twelve) months 0% 0%    
  (iv) Dullavcherra T.E. at Damchera  , Karimganj District. (Gr. V)  4059-01-051-2036-000-13-99-SOPD-G-V-GA AA/PWB_ 2022-23(I)_ 1415 dt.17.08.2022 61.06400 (L) 5810000.00 SBC/CS/ 2022-23/05/456/Gr -V/459 dt.10.10.2022 Sri Sourav Das 12 (twelve) months 0% 0%    
  (v) Goombhira T.E., Karimganj District. (Gr. IV)  4059-01-051-2036-000-13-99-SOPD-G-V-GA AA/PWB_ 2022-23(I)_ 1416 dt.17.08.2022 61.06400 (L) 5810000.00 SBC/CS/ 2022-23/05/456/Gr -IV/494 dt.29.10.2022 Sri Sourav Goswami 12 (twelve) months 0% 0%    
  UNDER M.S.D.P. MRS (KARIMGANJ DIST.)              
1 Construction of Model Residential School Building under MSDP at Ramkrishna Nagar, Karimganj, Package No. MRS/18 2575-Other Special Areas Programme-02-Backward Areas-800-Others Expenditure-2919-Multi-Sectoral Development Programme for Minorities in selected Minority Concerned Districts-092-35-Grants for creation of Capital Assets-99-Others (Central Share-CSS) during 2017-18 under Grant No. 42 WMD-18012/2/2018-WMD(Part)/9 dt.17.03.18 Rs.3042.69 (L) 288110126.00 BPM.45/ 2019/10 dt.09.07.19 M/S. Tribeni Construction Ltd. 24 months 58.0% 60.0% 1334.57 (L) 1334.57 (L) The Contractor is instructed to maintain the slope with temporary protection work such as Bamboo palasiding etc. However, revised estimate incorporating RCC Retaining wall in most vulnerable portion of slope has been sent to the C.E. PWD Building for approval.  Initially, the work was delayed  as the site was not accessible for carrying construction materials and the contractor had to do additional work of construction for approach road to the site including other land development works. Moreover it invariably required to provide immediate slope protection work before taking up further construction work. Also till date final demarcation is not done yet by the R.K. Nagar Circle Office and the work remain suspended for the several times during COVID-19. . Presently Work is in progress.
  MSDP (I.T.I. in Karimganj District)                    
1 Construction of Proposed I.T.I. at Eraligool in Karimganj District for the year - 2012-13 2575-other Spl. Areas Programmee-02-Backward areas-001-Direction & Admn-III-Centrally Sponsoured Scheme-2919-Implementation Dev. Scheme in Minority Concentrated Dist. under Multi Sectorial Dev. Programmee-35-Grant-in-aid (Capital Assets) during 2013-14 WMD.155/
2013/7 dt.22.08.2013
Rs.429.70 (L) 376.112 (L) PWO No. BPM.48/
2012/20 dt.28.02.14
Sri Abdul Quddus 12 months 70.5% 70.5% 260.00 (L) 260.00 (L) Deputy Commissioner Karimganj is requested to provide a suitable land for construction of Girls Hostel so as to complete the balance work. All the works such as administrative building,  Grade-IV Qtr. etc. are completed except Girls Hostel due to non availability of land.
As such work was withdrown by C.E. PWD Building.
  MSDP (Girls Hostel in Karimganj District)                    
1 Construction of 100 bedded Girls Hostel at (i) Shah Badaruddin High School, Badarpur                                  (ii) Bhanga H.S. School, Bhanga under MSDP in Karimganj District. 2575-other Spl. Areas Programmee-02-Backward areas-001-Direction & Admn-III-Centrally Sponsoured Scheme-2919-Implemented Dev. Scheme in Minority Concentrated Dist. under Multi Sectorial Dev. Programmee-35-Grant-in-aid (Capital Assets) during 2013-14 WMD.68/
2013/31 dt.18.06.2013
Rs.316.00 (L) 302.69 (L) BPM.63/
2013/8 dt.24.10.13
M/S. J.J. Construction 12 months 27% 27% 81.00 (L) 81.00 (L) It has been recomended to the higher authority for termination contract at contractor's own risk and cost. Contractor prayed for withdrow the work. 
  UNDER M.S.D.P. 12th PLAN (KARIMGANJ DIST.)              
1 Construction of RCC Delivery Room with Neonatal Room at Kaliganj Hospital under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.20.00 (L) 1980189.00 SBC/CS/
2017-18/17/525, dt.14.03.18
Sri. Fajal Hussain 6 months 40% 45%     As per the review meeting  the concerned  Contractor  committed to complete the work within Dec'2022. The Contractor has been delaying the wok since inspection. As such notice has been served to the contractor by imposing liquidity damage.
2 Construction of PHC Building at Nagrabazar under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.62.48 (L) 6184941.60 SBC/CS/
2017-18/16/418/Gr.-V/547, dt.19.03.18
M/S. S.Y. Const. 18 months 100% 100% 31.26 (L) 31.26 (L)   Work completed .
3 Construction of PHC Building at Kurtikuchi under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.62.48 (L) 6185506.20 SBC/CS/
2017-18/16/418/Gr.-III/551, dt.19.03.18
M/S. S.Y. Const. 18 months 100% 100% 31.24 (L) 31.24 (L)   Work completed &
handed over
4 Construction of Building at Makunda Chiristian Hospital under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.50.00 (L) 4890684.36 SBC/CS/
2017-18/16/418/Gr.-IV/548, dt.19.03.18
Sri. Monish Das 18 months 100% 100% 25.00 (L) 25.00 (L)   Work completed &
handed over
5 Construction of Girls Hostel (50 bedded) at Patharkandi College, Vill-Rajbari under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.78.00 (L) 7662455.65 SBC/CS/
2017-18/16/418/Gr.-I/549, dt.19.03.18
M/S. S.Y. Const. 18 months 99% 99% 38.05 38.05 Notice issued to the Contractor has been instructed to complete the work within Dec'2022. Civil work almost complete. However electrical work was kept pending by the contractor since long. Recently the contractor has started the electrical work.
6 Construction of RCC Hospital Building at Bhanga as per NRHM norms under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.50.00 (L) 4931000.00 SBC/CS/
2018-19/08/305, dt.26.12.18
Fazal Hussain 10 months 81% 81% 25.00 (L) 25.00 (L) Notice issued to the Contractor has been instructed to complete the work within Dec'2022. In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Oct'22.
7 Construction of CHC at Badarpur under MSDP 12th Plan   WMD.46/
2016/25, dt.09.03.17
Rs.25.51 (L) 2515554.58 SBC/CS/
2018-19/03/ 120/178, dt.21.09.18
Sri. Fazal Hussain 6 months 50% 55%     Notice issued to the Contractor has been instructed to complete the work within Dec'2022. In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Nov'22.
8 Construction of Medical Sub-Centre at Bazarghat Sub-Centre as per NRHM norms in Dullavcherra Deb. Block Karimganj under MSDP 12th Plan for the year 2016-17 (Group No. II)   WMD.46/
2016/25, dt.09.03.17
Rs.14.75 (L) 1460396.00 SBC/CS/2017-18/17/527
dt.14.03.18
Sri. Taher Ahmed Siddiquey 6 months 90.0% 91.0% 7.37 (L) 7.37 (L) Notice issued to the Contractor has been instructed to complete the work within Dec.  '2022. In the review meeting sated 14/07/2022. The contractor has given verbal commitment to complete the work witin Aug'22.
9 Construction of PHC Building at Balia Bazar under MSDP 12th Plan in Karimganj Dist.       8018719.00 SBC/CS/ 2019-20/14/ 318/393
dt.20.01.20
Sri. Shahid Ahmed Tapader 18 months 42% 42% 33.50 (L) 33.50 (L) Balance work estimate under preparation. Work withdrawn. Balanced work estimate will be submitted soon.
10 Construction of School Building of Balipipla High School under PMJVK (MSDP) 12th Plan in Karimganj Dist.   WMD.75/2017/7 dt.07.03.2017 5000000 4937997.00 SBC/CS/ 2021-22/06/399
dt.29.12.21
M/S. AKECON INDIA 12 months 55% 60%       Work is in progress
  Health Deptt. ( Karimganj District )                      
1 Upgradation of 24 Nos. of existing Hospitals for setting up of ICU's for treatment of patents of COVID-19 under Assam Critical Care project 2020 at Karimganj (Package No. DIS-COV-19/21) 4210-Co. on M&HP-03-MET&R-001-Direction & Admn.-0172-HQ Estt-070-COVID-19-13-Major works-99-Others under CSS (NESIDS) for the FY 2020-21 HLB.149/2020/Pt/446 dt.08.10.2020 15789.31 (L) 51658665.00 GMC.40/2020/21 dt.13.11.2020 Sri. Abdul Matin 4 (four) months 95% 95%     Contractor is instructed resume the work  immediately and to complete the balance work with in Dec'22. ICU Unit  work completed & handed over. However other ancillary works are kept pending by the contractor due to non receipt of any payment against the work done so far.
2 Establishment of 42 bedded Dedicated care Unit (30  o2 Supported beds + 8HDU + 4 PICU) in Karimganj District.  (Gr.-IV)   NHM-32048/3/ 2021/Construction-NHM/58  Dt.20.01.2022 Rs. 85,80,763.00 Rs. 84,09,147.74  SBC/CS/2021-22/09/376/
Gr-IV/90 dt.01.01.2022
Nasim Uddin Ahmed     3 months 71% 75%     A notice has been served to the contractor to complete the work  with in Sept'22. Initially,Work was delayed due to delay in handing over of site.  Presently, the work is in progress.
3 Establishment of RT PCR Laboratory in Karimganj District. (Gr.-V)   NHM-32048/3/ 2021/Construction-NHM/58  Dt.20.01.2022 Rs. 11,98,430.00 Rs. 11,74,461.40  SBC/CS/2021-22/09/376/Gr-V/69 dt.24.01.2022 Biplab Banik     3 months 100% 100%       Work Completed
4 Design, Supply, Installation  & Commissioning of 10KL Cryogenic Tank, MGPS and other support system at Civil Hospital in Karimganj District for the dedicated 32/42 bedded Pediatric care unit . (Gr.-II)   No. NHM-32048/3/2021/Construction-NHM/58  Dt.20.01.2022 Rs. 80,00,000.00 Rs. 70,40,000.00   SBC/CS/2021-22/10/403/85/
Gr-II/143 dt.28.02.2022
M/S AKECON INDIA, Prop:- Equbal Uddin 3 months 15% 15%     Drawing for  Oxygen tank received on  28th Sept'2022. Work is in progress.
  EVMs & VVPATs (KARIMGANJ DIST.)            
1 Construction of Godowns/Warehouse for proper storage of EVMs & VVPATs in the 50 Election Districts of Assam for the year 2017-18 (DEO Karimganj) 4059-60-Other Bldgs.-051-Constn.-2286-Constn. Of warehouse for EVM-000-13-Major works-99-others-SOPD-G-GA-KN/NN/BN-V during 2017-18 ELA.36/2015/321, dt.26.03.2018 Rs.218.13 (L) 20447166.00 PWO No. CS/T/BD/ 06/2018/6, dt.23.05.18 Sri. Abdul Quddus 7 (Seven) months 65% 75%     An updated work programme has been  submitted to D.C. Karimganj with a period completion, due to delay in handing over of site, heavy rain in the month of May, June, July'22. Initially, the contractor could not started the work due to unexpected long time delay of 3 & 1/2 years in handing over of site. However work was started on last week of January'22 and presently, work is in progress. 
  MINI STADIUM                          
1 Construction of Mini Stadium at Ramkrishna Nagar under Ratabari LAC, (District-Karimganj), Assam.       12,10,77,142.00 CS/T/TB-I/40/2022/18
dt. 31/10/2022.
Abdul Bachit 18 months 1% 1.5%       Work is in progress
2 Construction of Mini Stadium at Uttar Sepenjuri, Patherkandi  LAC, (District-Karimganj), Assam. 4059-60-051-4548-000-13-99-SOPD-G-V-GA AA/PWB_2022-23(I)_1535 1268.97484(L) 12,10,94,909.00 CS/T/TB-I/35/2022/12
dt. 04/11/2022.
Abdul Quddus 18 months 1% 1.5%       Work is in progress
4059-60-051-5247-252-05-03-SOPD-G-V-GA 38.32116(L)
  Total=1307.296(L)
  District Science Centre (Karimganj Dist.)              
1 Land development and Construction of boundary wall for Karimganj Distric Science Centre    STE.76/2018/Pt-V/34 dt.29.11.2018   239.70 (L) SBC/CS/2011-22/04/282/336 dt.09.11.21 M/S. Shristy Enterprise           District Scince centre is requested to handover encumbrance free site to PWD Building to start the construction of the said work. Also Circle officer, Karimganj also requested to make the site encrochment free. The Director of ASTE Council instructed  to PWD Building  not to start  any  work as the plot of land is now  under subjudice with the  Misc.Case No. 449/2021 arising out of  T.S. No.485/2021(Bakul Nath and other  VS. The state  of  Assam & Others ). 
2 Construction of Eleven (11) Nos. of District Science Centre at Karimganj, Package No. GMC-11 Nos. DSC 5425-00-800-3103-600-13-99-SOPD-G-V-GA AA/ST_2019-20(I)_07 dt.27.11.19 15042.84 822.77 (L) GMC.8/2020/43 dt.03.06.21 M/S. North East Plantation & Commercial Pvt. Ltd.          
  District Jail Karimganj                          
1 Construction of Double storied administration office building with prisoner interview room go down, doctor's chamber with at least 10 (Ten) bedded hospital at district jail, Karimganj.   AA/PRI_2020-21(I)_111 Dt. 10/09/2022. 147.82(L) 144.74(L) SBC/CS/ 2020-21/04/210/322
dt. 17/12/2020.
Sri Harihar Deka 18 months         The Superintendent of Jail is reaquested to provide NOC from the Jail authority to start the said work as well as to ensure proper security arrangement during construction vide T.O.Dt. 01/09/2022.  The work could not be started due to non receipt of  NOC from the Jail authority.
  B.A.D.P. ( Karimganj District )            
1 Construction of old Tourist Centre at Historical Malegarh Crematorium for Rs.40.00 lacs under BADP 2019-20 of Karimganj district   AA/DBA_2020-21(I)_512 dt.18.11.2020 40.00 (L) 3951519.00 SBD/TB/CS/ 2020-21/ 19/272 dt.25.02.21 Sri. Ratnadeep Das Purkayastha 6 months 65% 95%     Notice served to the contractor on 09/08/2022 to expedite the work and complete the work within Dec'2022. Initially,Work was delayed due to delay in handing over of site. Presently Work is in progress
2 Construction of BOP Camp at Choto Bubirbond 4575-02-001-0678-000-13-01-SOPD-ODS-V-GA” for the financial year 2021-22 AA/DBA_2021-22(I)_684 dt.11.08.2021 44.99 (L) 44,56,349.00  SBD/TB/ CS/2021-22/04/140 dt.01.10.21 Samsul Haque Choudhury 6 Months         Contractor was instructed to start the work immediatly and complete the work within 31.12.2022. Initially,Work was delayed due to delay in handing over of site. Now, the site has been handed over to the contractor in last month and he is instructed to start the work immediately. 
3 Construction of Ratabari Anchalik Nadwa Office in Karimganj Dist. under DCP for Development of Inter-State Border area during 2013-14 (Group-A)       297000.00 SBD/TB/
CS/14-15/
10/1061
Dt.28.01.15
Sri. Tahir Ahmed Khan 45 days 70% 70%     It has been recomended to the higher authority for termination contract at contractor's own risk and cost. The contractor has totally failed to execute the work and stopped the work since Oct. 2021 . Although several communication was made from this end but concerned contractor has not responded , also he rejected  the Phone calls. 
4 Construction of Open Community Hall (Assam type) at Solgai T.E. under Indo-Bangladesh Border Area under Lowairpoa Block at Karimganj District under BADP (SCA) for the year 2015-16 (Group No. II)       1287000.00 SBC/CS/
2016-17/ 11/457, dt.27.03.17
Sri. Debjani Das Roy 90 days 0% 0%     Work already withdrown. The work was withdrawn as no work was done by the contractor. Revised estimate submitted to D.C. Karimganj on 18.06.2020 for approval. 
5 Construction of Community Hall near Pallimangal Club at Patharkandi under Interest accrued against BADP  Fund in Karimganj District (Group No. I)   DBPD.94/2018/ BADP/108 dt.05.03.2019 10.00 (L) 984400.00 SBD/TB/CS/ 2019-20/1/2705
dt.09.08.19
Sri. Sushanta Sekhar Paul 90 days 0% 0%     It has been recomended to the higher authority for termination contract at contractor's own risk and cost. Contractor has not yet started any work and now he has prayed for withdraw the work due to obstruction of public & price hike of the materials & labour
  UNDER 13TH FINANCE COMMISSION (B.A.D.P.) (Karimganj Dist.)                    
1 Construction of Community Hall under Thirteen Finance Commission in Karimganj District of Indo-Bangla Boarder for 2011-12 (Gr-A)   DBA.230/2011/5                                                   dt.4.1.12 4000000.00 3960109.00 SBC/CS/11-12/58/905, dt.18.1.12 Sri. Paresh Chandra Ghosh 2            ( two ) months 80% & 65% 80% & 65% 20.00 20.00 It has been recomended to the higher authority for termination contract at contractor's own risk and cost. Penalty imposed
Jerjeri G.P - 2 Nos.  
Dengarbond G.P - 2 Nos.   100% & 100% 100% & 100%
Balipipla G.P   55% 55%
Lowairpoa G.P - 2 Nos.   75% & 100% 75% & 100%
  CM's Special Package for Barak Valley during 2013-14 (Karimganj Dist.)            
1 Upgradation of SC/SD/PHC to Community Hall Centre (Phase-I) in Barak Valley under CM's Special Package at R K Nagar CHC in Karimganj District under Annual Plan 2013-14 4210-Co-on-Medical & PH-01-Urban Health-Service-001-Direction & Admn.-172-HQ-Estt.
(ii) CM's Spl. Package for Barak Valley-543-works-13 Major work Plan General for 13-14
HLA.130/
2014/93
Dt.01.03.2014
Rs.330.00 (L) 314.69 (L) GMC.32/
2014/20
Dt.04.03.15
Sri. Abdul Quddus 18 (eighteen) months 95% 98% 60.697(L) 60.697(L) 80% payment against the executed work is pending since March 2015. However, the contractor has committed to complete the work within November '2022. Work is in progress
2 Cosntruction of Swimming Pool in Karimganj Dist. under CM's Special Package for Barak Valley for the year 2014-15   No. DB(B)/19/
2013/Pt-I/13
Dt.24.02.15
Rs.2.00 Crore 19660000.00 BN/06/2015/37
Dt.25.01.16
Sri. Iftakur Rahman 12 months 97% 97% 166.75 (L) 166.75 (L) Civil works completed in Feb. 2022 and electrical work is in progress. The contractor committed to complete the work within November 2022. Work is in progress
3 Construction of Market Complex and Pucca Drain in and around the Bazar area for letting out dead water at Kaliganj Bazar 4059-01-office-Building-101-Constn. Gen. Pool Accomodation-0121-Building (PW)-462-Cms Spl. Package for Barak Valley -13-Major works-99-others-state share, SOPD-G during the year 2017-18
DB(B).19/2013/12 Dt.11.11.13

Revised A.A. No.DB(B).101/ 2017/Pt-I/20 Dt.31.7.17
Rs.245.76 (L) 24310731.00 BN/144/
2013/14 Dt.15.02.14
M/S. J & J Const. 10 (ten) months 80% 80% 140.543 (L) 140.543 (L) It has been recomended to the higher authority for termination contract at contractor's own risk and cost . Contractor prayed for withdrawal of the work. 
4 Construction of Market Complex and Pucca Drain at Anglar Bazar in Karimganj District DB(B).19/2013/13 Dt.11.11.13 Rs.200.00 (L) 19707727.00 BN/145/ 2013/13 dt.15.02.14 Mujibur Rahman 10 (ten) months 30% 30% 55.09 (L) 55.09 (L) It has been recomended to the higher authority for termination contract without penalty  . The concerned contractor is not  willing  to do the remaining work as the land is subjudiced for last five years
5 Construction of Mini Stadium at Marjatkandi Public Higher Secondary School in Karimganj District under CM's Special Package for Barak Valley during 14-15 DB(B).19/
2013/Pt/11
Dt.24.02.15
Revised A.A. No.DB(B).101/ 2017/Pt-I/21 Dt.31.7.17
Rs.1.00 Crore 9896825.00 BN/04/ 2015/10 dt.10.04.15 M/S. J&J Construction 9 (nine) months 50% 50% 50.04 (L) 50.04 (L) It has been recomended to the higher authority for termination contract at contractor's own risk and cost . Contractor prayed for withdrawal of the work. 
6 Construction of RCC Community Hall with Library at Marjatkandi and RCC Community Hall at Chandrapur Bagbari, Gilaijan and RCC Guest House at Kuchilargool in Karimganj District under CM's Special Package for Barak Valley for the year 2014-15 4059-01-office-Building-101-Constn. Gen. Pool Accomodation-0121-Building (PW)-462-Cms Spl. Package for Barak Valley -13-Major works-99-others-state share SOPD-G during the year 2017-18 DB(B).19/
2013/Pt-I/17
Dt.24.02.15

Revised A.A. No.DB(B).101/ 2017/Pt-I/19 Dt.31.7.17
Rs.1.00 Crore 98.28 (L) BN/10/
2015/11
Dt.02.05.15
M/S. J&J Construction   82% 82%     It has been recomended to the higher authority for termination contract at contractor's own risk and cost . Contractor prayed for withdrawal of the work. 
7 Construction of 100 bedded Multistoried Boys Hostel at Kaliganj in Karimganj District under CM's Special Package for Barak Valley (Phase-II) for the year 14-15 DB(B).19/
2013/Pt-I/10
Dt.24.02.15
Revised A.A. No.DB(B).101/ 2017/Pt-I/18 Dt.31.7.17
Rs.2.00 Crore 197.38 (L) BN/03/
2015/13
Dt.10.04.15
M/S. J&J Construction   54% 54% 84.191 (L) 84.191 (L) It has been recomended to the higher authority for termination contract at contractor's own risk and cost . Contractor prayed for withdrawal of the work. 
8 Construction of Swasan at Maizgram & Beautification of Town Idgah, Swahid Bedi & Emersion Ghat & Community Hall etc. in Karimganj Dist. under CM's Special Package for Barak Valley for the year 2014-15   DB(B).19/
2013/Pt-I/24
Dt.03.03.15
Revised A.A. No.DB(B).101/ 2017/Pt/2 Dt.31.7.17
Rs.550.00(L) 52700000.00 FWO No.
BN/09/2015/30
Dt.29.12.15
M/S. Modern Construction Co. 12 months 23% 23%     Intend to Termination of Contact - Notice   was served on 08/08/2022 at contractor's own risk and cost . The concerned contractor is not willing to do the remaining work. Also the completion time of the work  has already been expired.
  UNTIED FUND in Karimganj District                    
1 Construction of Bishnupriya Manipuri Community Hall at Patharkandi in Karimganj Dist. under Untied Fund for 2016-17 (Gr. No. 2)   No. KDP.263/UF/
2016-17/65, dt.15.06.2017
100.00 (L) 9746347.00 No. SBC/CS/
2017-18/05/195
dt.05.08.17
Sri. Bimal Sinha 90 days 90% 98% 50.94 (L) 50.94 (L) Final Notice served to complete the work within Dec 2022. Civil works were completed six months ago. Only electrical transformer installation work is pending, which is now under progress. 
2 Construction of Swami Vivekananda Audtorium and Guest House near Swami Vivekananda, Sonakhira, Patharkandi under Untied Fund for 2017-18 (Gr. No.II)   No.PD/DCP/30/ 2018/73 Dt.04.08.2018 7000000.00 6935177.00 No. SBC/CS/ 2018-19/ 07/190/375 dt.01.02.19 Sri. Bimal Sinha 12 Months  99% 100% 47.89 (L) 47.89 (L) Finall Bill submitted Work completed and handed over
  REVENUE DEPTT. (Karimganj Dist.)            
1 Construction of Circle Office building including Civil, Electrical works and brick boundary wall with Iron gate in respect of Circle Officer, Nilambazar Revenue Circle under Karimganj District 4059-01-051-0408-Revenue Deptt. 701-Const. of Circle Officer etc.-13 Major works-99-Non-Plan during year 2015-16 RRA.69/2014/42
dt.13.05.15
16696367.00 14079424.00 FWO No.
BN/69/
2014/14
Dt.18.03.15
Sri. Mojibur Rahman 12 months 70.5% 70.5% 39.96 (L) 39.96 (L) It has been recomended to the higher authority for termination contract . Main Office Building  work completed & handed over. However boundary wall is not done by the contractor due to non receipt any payment against the pending bills of the contractor since 2018 and now the Contractor is not willing to any work due to price hike.
  -Do- Soil Testing work       60000.00   Creative Engineers   100% 100% 60000.00 60000.00   Final payment made
                             
                             
                             
                             
                             
               ,Executive Engineer P.W.D.      
              Karimganj District Territorial Building Division,       
              Karimganj